medium10 pts · first answer countsproject-planningearned-valueearned-schedule

Earned schedule in months

Cumulative PV is ₹10 lakh after month 1, ₹25 lakh after month 2, ₹45 lakh after month 3 and ₹70 lakh after month 4. At the end of month 4, EV is ₹45 lakh. What is SPI(t)?