What a baseline is
easy
5 pts · first answer counts
project-planning
change-control
What a baseline is
What is a project baseline?
Choose one answer
A.
The first rough draft of the plan
B.
The actual cost spent so far
C.
The approved version of the scope, schedule or cost plan, used to measure performance and changed only through change control
D.
The project manager's private, unshared estimate
Submit answer
Report a problem
← Previous
Purpose of a change request
Next →
When waterfall fits
All easy Project Manager questions
Discussion
0
Join free
to post in the discussion.
Related questions
Assumption or constraint?
Project Manager
Purpose of a change request
Project Manager
A 'small' extra request
Project Manager
Rolling out a rebrand
Graphic Designer
UAT finding: defect or change?
Business Analyst
More Change Control questions