medium10 pts · first answer countsproject-planningearned-valueearned-schedule
Interpolating earned schedule
Cumulative PV is ₹25 lakh at month 2 and ₹45 lakh at month 3. Current EV is ₹35 lakh. What is the earned schedule (ES)?