hard20 pts · first answer countsproject-planningschedule-compressioncritical-path
Crashing two parallel paths
The network needs to come down from 10 to 8 days. Each activity can be crashed by up to 2 days at the cost shown per day. What is the minimum crashing cost?
A: 3 days, then B and C in parallel B: 4 days (crash ₹8,000/day) C: 3 days (crash ₹2,000/day) D: 3 days, after B and C (crash ₹12,000/day) A crash cost: ₹11,000/day