Point of total assumption
A fixed price incentive fee contract has target cost $100,000, target profit $10,000, target price $110,000, ceiling price $120,000 and a buyer/seller share ratio of 70/30. What is the point of total assumption (PTA)?
PTA = target cost + (ceiling price - target price) / buyer share