hard20 pts · first answer countsrisk-managementquantitative-analysis
Build or buy decision tree
Buying a tool costs a certain $120,000. Building it costs $80,000 with a 70% chance, but a 30% chance of overruns bringing the total to $180,000. Based on expected monetary value, what should you choose?