hard20 pts · first answer countsprioritisationcost-of-delaywsjf
Total cost of two orders
A costs ₹10 lakh a week to delay and takes 5 weeks; B costs ₹4 lakh a week and takes 1 week. Each item's delay cost runs until it is finished. What is the total delay cost if B goes first, versus A first?