Which changes the PM can approve
The PM may approve changes alone if the cost is up to ₹2 lakh AND the schedule impact is up to 5 days. Which of these changes can the PM approve without the CCB?
A: cost ₹1.5 lakh, 3 days later B: cost ₹0.5 lakh, 8 days later C: cost ₹3 lakh, no delay D: cost ₹1 lakh, 5 days later