hard20 pts · first answer countsrisk-managementquantitative-analysiscontract-risk
Expected value of a delay penalty
A ₹50 lakh contract has liquidated damages of ₹2 lakh per week of delay, capped at 10% of contract value. There is a 30% chance of a 4-week delay. What is the EMV of this threat?