hard20 pts · first answer countsschedule-riskstakeholder-management

Committing to a date

Monte Carlo analysis shows a 50% chance of finishing by 14 June and an 80% chance by 2 July. The deterministic plan says 1 June. The sponsor asks for a date to tell customers. What should you recommend?

Choose one answer