EAC using CPI and SPI
BAC = $1,000,000, PV = $500,000, EV = $400,000 and AC = $500,000. A fixed deadline means schedule pressure will also affect cost. Using the formula that factors in both CPI and SPI, what is the EAC?
EAC = AC + (BAC - EV) / (CPI x SPI)