hard20 pts · first answer countsagileagile-metricsearned-value
Earned value on an agile release
A release is planned at 200 story points with a budget of ₹50 lakh. After some sprints, 80 points are done and ₹25 lakh has been spent. What is the cost performance index (CPI)?