medium10 pts · first answer countsprioritisationwsjf
Working out WSJF
In WSJF, Cost of Delay = business value + time criticality + risk reduction, and WSJF = Cost of Delay / job size. A: 8 + 5 + 3, size 8. B: 5 + 8 + 2, size 3. C: 10 + 2 + 3, size 5. Which should go first?