medium10 pts · first answer countsprioritisationweighted-scoring
Weighted scoring
Criteria weights are revenue 50%, retention 30% and strategic fit 20%. Scores out of 10: A = 8, 4, 6. B = 5, 8, 7. C = 6, 6, 9. Which project scores highest?