medium10 pts · first answer countsprioritisationproject-planning
Slack on a task
In the same plan (A 3 days, then B 4 and C 6 in parallel, then D 2), how much slack does task B have?
Discussion 0
Join free to post in the discussion.
In the same plan (A 3 days, then B 4 and C 6 in parallel, then D 2), how much slack does task B have?
Join free to post in the discussion.