hard20 pts · first answer countsprioritisationcapacity-planning
When value per effort misleads
You have 6 weeks. A: value 11, 5 weeks. B: value 6, 3 weeks. C: value 6, 3 weeks. D: value 3, 2 weeks. Picking by highest value per week first selects A. Which plan gives the most value?