Cost of delay divided by duration

Feature A has a cost of delay of ₹10 lakh a week and takes 5 weeks. Feature B costs ₹4 lakh a week to delay and takes 1 week. Using CD3 (cost of delay / duration), which comes first?

Choose one answer