medium10 pts · first answer countsvariance-analysisbudgeting

Flexing the budget for volume

The budget assumed 1,000 units at a variable cost of 50 per unit. Actual output was 1,200 units and actual variable cost was 62,000. What is the variable cost variance against a flexed budget?