hard20 pts · first answer countsfinancial-statementsrevenue-recognition
Revenue on a construction contract
A fixed-price contract is worth ₹10 crore with total estimated cost of ₹8 crore. Costs incurred to date are ₹2 crore, and progress is measured by costs incurred. How much revenue is recognised to date?