medium10 pts · first answer countsrevenue-recognitionvariable-consideration
Estimating an all-or-nothing bonus
A contractor earns a ₹50 lakh bonus only if a bridge is finished by 31 December; otherwise nothing. Which method best estimates this variable consideration?