medium10 pts · first answer countsscope-management
Deemed acceptance after silence
Your contract says a deliverable is deemed accepted if the client raises no defects within 10 working days. The client stays silent for 15 days, then asks for a feature to be reworked because it is "not accepted". What is your position?