Skip to content
RED SAGSkills
medium10 pts · first answer countscritical-pathscheduling

Free float of an activity

Using the same network (A 3 days; B 5 days and C 2 days after A; D 4 days after B and C), what is the free float of activity C?

Choose one answer

Discussion 0

Join free to post in the discussion.

Related questions