Schedule and cost variance

BAC is $200,000. By today the plan said 50% would be done, but only 40% is complete. Actual cost so far is $90,000. What are SV and CV?

BAC = 200,000
Planned complete = 50%
Actual complete = 40%
AC = 90,000