medium10 pts · first answer countsearned-value
Schedule and cost variance
BAC is $200,000. By today the plan said 50% would be done, but only 40% is complete. Actual cost so far is $90,000. What are SV and CV?
BAC = 200,000 Planned complete = 50% Actual complete = 40% AC = 90,000