hard20 pts · first answer countsfirmwarertosscheduling
Is this task set schedulable
Three periodic tasks run under rate-monotonic priorities with execution time C and period T of (1 ms, 4 ms), (2 ms, 8 ms) and (3 ms, 12 ms). What does the Liu and Layland bound say?