hard20 pts · first answer countshigh-availabilitycapacity-planning
Capacity to survive losing a zone
Peak load is 6,000 requests per second, spread across 3 availability zones. You must handle peak even with one whole zone down. What total capacity must you provision?
Discussion 0
Join free to post in the discussion.