hard20 pts · first answer countsinternal-controlssampling
Sample rate below, upper limit above
Tolerable deviation rate is 5%. In a sample of 50 you find 2 deviations (4%). Using statistical tables at 95% confidence, the upper deviation limit is about 12%. What do you conclude?